Thursday May 26, 2022
Road work will begin early next week starting with grading.
Following grading the next step will be culvert cleaning and replacement
and ditching on the inflow and outflow at most of the culverts.
Then contouring and fill is needed on some areas of the road prior to the
gravel being dumped and graded. Equipment will be on the road in several
places during this time of construction.
This construction work will take time and hopefully will be completed by
mid June.
Travel on the road system might see some delays during this work so be
cautious and patient during your travel to the lake.